Force Majeure in Petroleum Operations and Its Effect on Time Limits

Banko Law Firm & Mediation2 min read30-Day Petroleum & Energy Law · Day 23

Petroleum exploration and production are long-term, capital-intensive activities exposed to external factors. The effect of events beyond the right holder's control on licence terms and obligations is therefore an important part of the sector's legal risk assessment.

Under Article 16 of the Turkish Petroleum Law No. 6491, natural disasters or a state of war postpone the rights and responsibilities of the petroleum right holder for an equal period, in proportion to their effect on petroleum operations. The provision does not extinguish obligations in the event of force majeure; it postpones them in proportion to the event's effect on petroleum operations and for the duration of that effect.

The events expressly listed in the Law are limited to natural disasters and a state of war. Whether other events, such as epidemics, extensive administrative restrictions or supply chain disruptions, may fall within this scope should be assessed separately in light of the relevant regulations, administrative practice and the specific circumstances of each case.

Force majeure is also relevant to the sanction provisions of the Law. Consequences such as forfeiture of the guarantee for failure to perform the work programme, and revocation of a production licence where production does not start or is suspended, are set out in the Law as applying except in cases of force majeure.

Alongside the licence relationship, private law contracts such as joint operating and service agreements also contain force majeure clauses. In these contracts, the definition of force majeure, notice periods, documentation and termination rights should be drafted consistently with the administrative framework. Where the contract is silent, the provisions of the Turkish Code of Obligations No. 6098 on impossibility of performance and excessive difficulty of performance may come into play. In conclusion, to postpone rights and obligations on grounds of force majeure, the event must fall within the scope of the Law, its effect on petroleum operations must be demonstrated, and it must be notified to and documented with the authority in a timely manner. Clearly recording the duration and extent of the event's effect will be decisive in any potential dispute.

Sources · Kaynaklar

  • 6491 sayılı Türk Petrol Kanunu m.16, m.24/6-7
  • 6098 sayılı Türk Borçlar Kanunu m.136, m.138